Metro tunnelling completed between Ayanavaram and Otteri, ET RealEstate

June 14, 2024
0 Comments


<p>File Photo</p>
File Photo

CHENNAI: A tunnel boring machine named Anaimalai completed tunnelling between Ayanavaram metro and Otteri metro on Thursday and achieved a breakthrough as part of the 116.1km phase-2 project

A release said Anaimalai, which started tunnelling on October 23, 2023, built a 925metre-long tunnel and reached the shaft at Otteri metro.

CMRL managing director M A Siddique and other officials were present during the breakthrough event.

The stretch from Ayanavaram to Otteri is part of the 9km underground section on the 45.4km corridor-3 from Madhavaram Milk Colony to Siruseri Sipcot. A total of seven tunnel boring machines have been mobilised for tunnelling work in the stretch.

Phase-2 has three corridors covering 116.1km. A total of 23 tunnel boring machines will be used for tunnelling work in the project.

  • Published On Jun 14, 2024 at 12:00 PM IST

Join the community of 2M+ industry professionals

Subscribe to our newsletter to get latest insights & analysis.

Download ETRealty App

  • Get Realtime updates
  • Save your favourite articles


Scan to download App




Source link

Abhay Singh

Web Developer